19-04-2012 - After about a week of delays because of some messurment issues the frames have shown up on site. The chippies were on site straight away and marked out the slab.


About 30 minutes after taking the photo we had about 20mm of rain. Its a little frustrating as we have had perfect weather for the last week but no frames, now we have frames but bad weather... All the same the guys were able to start on standing up the frames.


Its a great feeling to walk through at least a small part of the house, having looked at it only on paper for the last 18 months I think its finally hit home that it is starting to come together. Also physically seeing the room sizes and layout is great, as with no real design experience its very hard to visualise how everything is going to work.
The trusses were scheduled to be delivered next week, but as you can see in the above photo they have been dropped off sometime late in the afternoon today..